9-16-89
Section 9-16-89 Performance bonds and bond releases. (a) After a surface coal mining and reclamation
permit application has been approved but before such a permit is issued, the applicant shall
file with the regulatory authority, on a form prescribed and furnished by the regulatory authority,
a bond for performance payable to the state and conditioned upon faithful performance of all
the requirements of this article and the permit. The bond shall cover all lands disturbed
by the surface coal mining operation and the amount of the initial bond shall be such to cover
that area of land within the permit area upon which the operator will initiate and conduct
surface coal mining and reclamation operations within the initial term of the permit. As succeeding
increments of surface coal mining and reclamation operations are to be initiated and conducted
within the permit area, the permittee shall file with the regulatory authority an additional
bond or bonds to cover such increments in...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-89.htm - 10K - Match Info - Similar pages

9-16-90
Section 9-16-90 Environmental protection performance standards. (a) Any permit issued pursuant
to this article to conduct surface mining operations shall require that such surface coal
mining operations will meet all applicable performance standards of this article, and such
other requirements as the regulatory authority shall promulgate. (b) General performance standards
shall be applicable to all surface coal mining and reclamation operations and shall require
the operation as a minimum to: (1) Conduct surface coal mining operations so as to maximize
the utilization and conservation of the solid fuel resource being recovered so that reaffecting
the land in the future through surface coal mining can be minimized; (2) Restore the land
affected to a condition capable of supporting the uses which it was capable of supporting
prior to any mining, or higher or better uses of which there is reasonable likelihood, so
long as such use or uses do not present any actual or probable hazard to...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-90.htm - 30K - Match Info - Similar pages

9-16-88
Section 9-16-88 Permits - Review and appeal of applications. (a) At the time of submission
of an application for a surface coal mining and reclamation permit, or revision of an existing
permit, pursuant to the provisions of this article, the applicant shall submit to the regulatory
authority a copy of his advertisement of the ownership, precise location, and boundaries of
the land to be affected. At the time of submission such advertisement shall be placed by the
applicant in a local newspaper of general circulation in the locality of the proposed surface
mine at least once a week for four consecutive weeks. The regulatory authority shall notify
various local governmental bodies, planning agencies, and sewage and water treatment authorities
or water companies in the locality in which the proposed surface mining will take place, notifying
them of the operator's intention to surface mine a particularly described tract of land and
indicating the application's permit number and where a...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-88.htm - 5K - Match Info - Similar pages

9-16-82
Section 9-16-82 Permits - Required; term; successor in interest; termination; renewal; application.
(a) No person shall engage in surface coal mining operations at a particular location except
as a subcontractor of the permittee of that location until such person has been issued a permit
by the regulatory authority for that location in accordance with the provisions of this section.
The term of a permit shall not exceed five years and shall authorize the permittee to engage
in surface coal mining operations within the permitted area, unless sooner suspended or revoked
in accordance with the provisions of this article. However, if the applicant demonstrates
that a specified longer term is reasonably needed to allow the applicant to obtain the necessary
financing for equipment and the opening of the operation and that the application is full
and complete for such specified longer term, the regulatory authority may grant a permit for
such longer term. A successor in interest of a...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-82.htm - 5K - Match Info - Similar pages

9-16-83
Section 9-16-83 Permits - Contents of application; reclamation plan; copy of application filed
for public inspection; insurance; blasting plan. (a) Each application for a surface coal mining
reclamation permit under this article shall be accompanied by a fee as determined by the regulatory
authority, but not to exceed the anticipated cost of reviewing, administering, and enforcing
the permit. In no event shall the permit fee be less than one thousand dollars ($1,000). The
regulatory authority shall develop procedures to enable the cost of the fee to be paid over
the life of the mine. The life of the mine means the term of the permit and the time required
to successfully complete all surface coal mining and reclamation activities and obtain a full
release of the performance bond for each bonded area. (b) The permit application shall be
submitted in a format prescribed by and satisfactory to the regulatory authority and shall
contain, among other things, all of the following: (1) The...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-83.htm - 13K - Match Info - Similar pages

9-16-72
Section 9-16-72 Definitions. The following words and phrases, unless a different meaning is
plainly required by the context, shall have the following meanings: (1) APPLICANT. Any person
or legal entity who or which applied for a license or a permit to engage in surface coal mining
operations. (2) APPROXIMATE ORIGINAL CONTOUR. That surface configuration achieved by filling
and grading of the mined area so that the reclaimed area, including any terracing or access
roads, closely resembles the general surface configuration of the land prior to mining and
blends into and complements the drainage pattern of the surrounding terrain, with all high
walls and spoil piles eliminated; water impoundments may be permitted where the commission
determines that they are in compliance with this article. (3) COAL BROKER and COAL SALES AGENCY.
Those persons whose principal business is the buying and reselling of coal, or the negotiation
or soliciting of coal sales between operators and purchasers; where...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-72.htm - 7K - Match Info - Similar pages

9-16-94
Section 9-16-94 Penalties. (a) Any permittee or operator who violates any permit condition
or who violates any other provision of this article, may be assessed a civil penalty by the
regulatory authority, except that if such violation leads to the issuance of a cessation order
under Section 9-16-93, the civil penalty shall be assessed. Such penalty shall not exceed
$5,000.00 for each violation. Each day of continuing violation may be deemed a separate violation
for purposes of penalty assessments. In determining the amount of the penalty, consideration
shall be given to the permittee's history of previous violations at the particular surface
coal mining operations; the seriousness of the violation, including any irreparable harm to
the environment and any hazard to the health or safety of the public; whether the permittee
was negligent; and the demonstrated good faith of the permittee charged in attempting to achieve
rapid compliance after notification of the violation. (b) A civil...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-94.htm - 7K - Match Info - Similar pages

9-16-96
Section 9-16-96 Designation of areas unsuitable for surface coal mining; right to petition;
review and public hearing; areas exempt from mining operations. (a)(1) The regulatory authority
shall establish a planning process enabling objective decisions based upon competent and scientifically
sound data and information as to which, if any, land areas of the state are unsuitable for
all or certain types of surface coal mining operations pursuant to the standards set forth
in subdivisions (2) and (3) of this subsection but such designation shall not prevent the
mineral exploration pursuant to the article of any area so designated. (2) Upon petition pursuant
to subsection (c) of this section, the regulatory authority shall designate an area as unsuitable
for all or certain types of surface coal mining operations if the regulatory authority determines
that reclamation pursuant to the requirements of this article is not technologically and economically
feasible. (3) Upon petition pursuant to...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-96.htm - 8K - Match Info - Similar pages

9-16-93
Section 9-16-93 Violations; inspection by authority; remedial actions; hearing; action by Attorney
General. (a) Whenever, on the basis of any information available to it, including receipt
of information from any person, the regulatory authority has reason to believe that any person
is in violation of any requirement of this article or any permit condition required by this
article, the regulatory authority shall immediately order an inspection of the surface coal
mining operation at which the alleged violation is occurring unless the same information is
available to the regulatory authority as a result of a previous inspection. When the inspection
results from information provided to the regulatory authority by any person, the regulatory
authority shall notify such person when the inspection is proposed to be carried out and such
person shall be allowed to accompany the inspector during the inspection. The regulatory authority
shall consult with all state and federal agencies charged...
alisondb.legislature.state.al.us/alison/CodeOfAlabama/1975/9-16-93.htm - 9K - Match Info - Similar pages

9-16-85
Section 9-16-85 Permits - Approval or denial by authority; filing of violation schedule; issuance
to mine on prime farm land. (a) Upon the basis of a complete mining application and reclamation
plan or a revision or renewal thereof, as required by this article, following public notification
and opportunity for a public hearing as required by Section 9-16-88, the regulatory authority
shall grant, require modification of, or deny the permit within 30 days and notify the applicant
in writing of its action. The applicant for a permit, or revision of a permit, shall have
the burden of establishing that his application is in compliance with all the requirements
of this article. Within 10 days after the granting of a permit, the regulatory authority shall
notify the local governmental officials in the local political subdivision in which the area
of land to be affected is located that a permit has been issued and shall describe the location
of the land. (b) No permit or revision application...